Viking Link Cable Reels Transported by Allelys – Heavy Lift News
4 Jan 2022

Viking Link Cable Reels Transported by Allelys

Allelys are supporting the Viking Link project by transporting cable reels to multiple
compounds across Lincolnshire.

The specialist transport scope of work began in October 2020 to identify suitable routes
from the port to the compounds. Allelys completed abnormal load route studies from the
Port of Boston to 24 different compounds across Lincolnshire.

Once the routes had been identified, Allelys engineered a transport solution using a
specialist reeling trailer in a 2 bed 4 configuration. The trailers enable the reel to sit on
rollers on the beam, which can be adjusted for different reel lengths. With reels weighing
up to 60te and measuring a maximum of 4.5m in diameter and 7.1m in length, the
equipment provided the flexibility required to successfully complete the transport to site.

 

 

To date, Allelys have completed the transport of 38 cable reels and will continue to support
the project into 2022.

“Route studies are an integral element to specialist transport projects and assist customers
during the planning phase,” explains Zac Smout, Project Manager at Allelys.

 

 

“We’re able to identify routes that are suitable for the cargo, measure pinch points along
the route and co-ordinate with the relevant authorities if any adjustments need to be
completed. These can include anything from trees being trimmed and street furniture being
temporarily removed through to designing overbridging solutions or gaining permission to
travel contraflow along parts of the route. With the Viking Link project having 24 different
compounds, this planning aspect at the beginning was crucial to the successful delivery of
the reels.”

The Viking Link project connects Bicker Fen substation in Lincolnshire and Revsing
substation in southern Jutland, Denmark to create a 1,400 MW high voltage direct current
(DC) electricity link and will be approximately 765km long.

 

 

Source Allelys

 