

Universal Cranes Adds Completely Overhauled Pre-Used Liebherr LTR 11200 to Fleet
With the LTR 11200, Universal Cranes has added a completely overhauled pre-used crane to its fleet.
With the new, versatile crane, they can handle these applications in a wide range of sectors – from infrastructure to industrial projects,” says Mark Happer, General Manager at Universal Cranes. He particularly appreciates the strong telescopic boom and the variable boom options. Ben Smith, National Operations Manager at Universal Cranes, adds: “With the LTR 11200, we can move the crane fully equipped on construction sites with steep terrain. The pedestal mode also allows us to carry out jobs without having to take the crawlers to the construction site.”
As an all-terrain model, the 1,200t crane combines maximum lifting capacity with the longest telescopic boom in the world. With its 100m long telescopic boom, Y-guying and quick-setup lattice extensions, the LTR 11200 was originally developed for erecting wind turbines. The setup times are significantly shorter than lattice boom cranes and comparatively low counterweights and space are required to erect the boom. Its different driving configurations enable this all-terrain crane to be transported at low cost all over the world. “Compared to other heavy-duty cranes, the crawler crane takes up less space for installation, as the telescopic boom requires less assembly space than a lattice boom crawler,” says Happer.

Due to limited space and critical time frames, the complex job required precise planning by Universal Cranes
One of the telescopic crawler crane’s first jobs for the Australian crane hire company was during the modernisation of a railway crossing in Brisbane, where it successfully installed bridge girders and thus mastered the challenges of a complex infrastructure project. Nine pre-cast concrete girders with a length of 35m and a weight of 76t had to be erected. The crane was equipped with a 28m long main boom, a 36m long luffing jib and 182t of ballast.
“The operation was carried out on behalf of Bielby Hull Joint Venture. We provided our customer with comprehensive support in assembly and lifting planning to ensure seamless execution of the work. The complex project was carried out during ongoing railway operations and required months of careful preparation and close collaboration with the key stakeholders,” reports Patrick Silver, Projects and Heavy Lift Division Manager at Universal Cranes.

The 1,200t crane was equipped with a 28m long main boom, a 36m long luffing jib and 182t of ballast
The bridge girders were stored on site prior to the installation date in order to minimise the risks during the operation due to the necessary rail closure. This meant that the lifts could be carried out without delay within the critical time window. “Our LTR 11200 was the ideal crane solution for this job: It is unrivalled in its load capacity class and can also be moved around the construction site. In this particular case, the area for the crane assembly was very limited, but thanks to its crawlers, the 1,200-tonne crane could be put into operation in an adjacent yard – far away from the rail corridor and the carriageway,” says Silver. In the end, the operation was successfully completed after two days as planned.

The Liebherr crawler crane installed a total of nine pre-cast concrete beams with a length of 35m and a weight of 76t
Universal Cranes has a total of 278 cranes in its fleets in Australia, New Zealand and Guam. 47 of them are from Liebherr. “We have always received excellent service and support from Liebherr. Our long-term relationships are based on shared values and trust. This encouraged us to buy an overhauled LTR 11200 from Ehingen – because we knew that Liebherr pre-used cranes are reconditioned with great care and therefore stand for the same high quality that we are used to from new cranes,” says Ben Smith happily. The National Operations Manager of Universal Cranes saw for himself during the reconditioning process on site in Ehingen: “We were impressed by the factory and the experienced staff – I had the impression that the team, from the project manager to the technician, put their heart and soul into their work.”
Featured Title photograph
The LTR 11200 modernised a level crossing in Brisbane.
Source