13 Nov 2020
A wind turbine blade being transported on a TeleMAX platform trailer by Faymonville in Australia. Photograph – Faymonville
Date 15 October 2018
The blades for the new wind turbines at the 453MW Coopers Gap Wind Farm have been delivered with a TeleMAX platform trailer by Faymonville.
The largest blades are 67.2m long and weigh 22t. When it’s completed, the wind farm at Cooranga North will be one of Australia’s largest.
It’s expected to be fully operational by mid-2019. The project comprises of a total of 123 wind turbines, with 91 x 3.63MW turbines (137m rotor diameter) and 32 x 3.83MW (130m rotor diameter) turbines – a total of 369 blades transported.
Photographs – South Burnett Times
source Faymonville
is part of the Colas Group