ST³ Offshore 1,905 Tons Suction Bucket Jacket Borkum Riffgrund 2 Wind Farm 3/3 – Heavy Lift News
15 Apr 2018

ST³ Offshore 1,905 Tons Suction Bucket Jacket Borkum Riffgrund 2 Wind Farm 3/3

14 April 2018

Heavy Lift & Second Transport Cuxhaven (Germany) Ørsted “OWF Borkum Riffgrund 2” Wind Farm 1,500 Tons

Heavy Lift Crane ST³ Offshore Szczecin Highest Gantry Crane in Europe. Najwy?sza suwnica w Europie

Gantry Crane: Van Haagen Kraan BV Breda SWL: 1,400 Tons 120m↑(4x 350 Tons 95 m↑, 6 m/s)← 48 m →.

The winches are driven by motors with a speed of 4500 rpm – 0,67 m/s, 200 kW). Electrical installation of 15kV in 2 pieces of 20 feet containers, Siemens PLC software.

Crane Operator’s Cab: Merford – NOVA 1.6 (L: 1692,7 x W: 1600 x H: 2286,6 mm)

Spreader Beams: Modulift Modular: MOD 400/600s (L: 8m, SWL: 600 Tons 14m↑ & 1MOD 800/1000 SWL: 1,000 Tons 15m↑ Schmidbauer GmbH & Co. KG & ALE Heavy Lift

Cranes: Demag AC-130-5, AC-250-5, Terex-Demag CC-3800 & SL-3800,

Modular Trailer: Goldhofer PST/SL-E (12+12 & 6+6 – axle load: 45 t -1 km/h, twin tires 215/75 R. 17,5) + 207 KW cummins Power Pack. Vehicle width: ←3 m→

Cargo: – External Platform – 15 Tons (18 x 9,6 x 1,5 m) – Jacket – 1,905 Tons (3x 635 T), 59,93 m↑, ← 28,27 m →, the size of the foundation head: 14 m

TUG: Euros (GT: 280 BP: 32 Tons), Boa Barge (GT: 490 BP: 65 T), Fairplay Towage & BOA Management AS Pontoon: Boa Barge 44 (DWT: 10,866 T GT: 4,479 – 91,44 x 30,48 x 6,09 m) BOA Management AS Total length of the tow assembly 152,76 m

Bulk Carrier: – KOM (142.14 X 22.26 m, GT: 10,220 DWT: 13,971 Tons ), Year Built: 1997 – Thalassic (224,9 X 32,26 m, GT: 42,751 DWT: 81,426 Tons), Year Built: 2009

The second loading & transport (Szczecin-Cuxhaven) of 3 lattice foundations, so-called “jackets” for the offshore wind farm – “Borkum Riffgrund 2”.

Watch the video below:

The “BR 2” offshore wind farm has a planned capacity of up to 450 MW. Out of 56 steel foundations on which wind turbines will be installed, 20 are truss foundations, the remaining 36 are monopiles. The used wind turbines will be the largest in German waters: 56 turbines with a capacity of 8 MW and 164-meter rotors will be provided by the company “MHI Vestas”. The offshore wind farm will produce CO2-free energy corresponding to the annual electricity consumption of 460,000 German households.

(PL) Drugi transport (Szczecin-Cuxhaven) 3 fundamentów kratownicowych tzw. “jacketów” dla morskiej farmy wiatrowej – “Borkum Riffgrund 2”. Morska farma wiatrowa “BR 2” ma planowan? wydajno?? do 450 MW. Spo?ród 56 stalowych fundamentów, na których instalowane b?d? turbiny wiatrowe, 20 to fundamenty kratownicowe, pozosta?e 36 to monopale. Wykorzystane turbiny wiatrowe b?d? najwi?kszymi na niemieckich wodach: 56 turbin o mocy 8 MW i 164-metrowych rotorach dostarczy firma “MHI Vestas”. Morska farma wiatrowa wyprodukuje woln? od CO2 energi? odpowiadaj?c? rocznej konsumpcji elektryczno?ci 460,000 niemieckich gospodarstw domowych.

(D) Der zweite Laden & Transport (Szczecin-Cuxhaven) von 3 Gitterfundamenten, sog “Jacken” für den Offshore-Windpark “Borkum Riffgrund 2”. Der Offshore-Windpark “BR 2” hat eine geplante Kapazität von bis zu 450 MW. Von 56 Stahlfundamenten, auf denen Windturbinen installiert werden, sind 20 Fundamente, die restlichen 36 sind Monopiles. Die genutzten Windräder werden die größten in deutschen Gewässern sein: 56 Turbinen mit einer Leistung von 8 MW und 164 Meter Rotoren werden von der Firma “MHI Vestas” zur Verfügung gestellt. Der Offshore-Windpark wird CO2-freie Energie produzieren, die dem jährlichen Stromverbrauch von 460.000 deutschen Haushalten entspricht.