Shodesh Shipping & Logistic Company Handles Large Break Bulk Cargo for Rooppur Nuclear Power Plant Construction – Heavy Lift News
3 Nov 2022

Shodesh Shipping & Logistic Company Handles Large Break Bulk Cargo for Rooppur Nuclear Power Plant Construction

Shodesh Shipping & Logistic Company, THLG member for Bangladesh, has successfully handled one of its biggest Break-bulk Consignments with the cooperation of their sister companies Shodesh Shipping Line, Shipping Agent, Rusani Enterprise, Customs Broker and Shodesh Carrier, Transport Company.

 

 

The consignment arrived at Chittagong Seaport on 22 July 2022 on board the vessel MV DIANA carrying 106 containers – 3,334 Ton, 13,053 Packages and Bulk Cargo for the Construction of Rooppur Nuclear Power Plant (RNPP), the country’s first nuclear power plant.

 

 

The cargo belongs to Bangladesh Atomic Energy Commission, the executor and three other official subcontractors of the RNPP. Out of 106 Containers, 50 were Carrier’s Owned Containers (COC) and 56 were Suppliers Owned Containers (SOC). Total 350 Vehicles were used to deliver the cargo to job site.

 

13,053 Packages

 

The work scope for the Shodesh Shipping & Logistic Company included:

  • Vessel Declaration
  • Port Clearance
  • Permissions management including Transit Permission from Bangladesh Atomic Energy Commission & Customs
  • Import & Tax Permissions
  • Customs Clearance
  • 24/7 Loading at Port
  • Transportation and Warehousing
  • 24/7 Unloading at Job Site

 

 

 

Source Shodesh Shipping & Logistic Company and The Heavy Lift Group (THLG)