Sarens Wind Farm Transport and Installation in Vietnam
Sarens was commissioned by Siemens Gamesa Renewable Energy to transport and install twelve G114-2.6MW wind turbine generators at the Dam Nai Wind Farm -II in Vietnam. With the second phase added, this wind farm is now the largest of its kind in the Southeast Asian country. The second phase, having a total investment of US$ 60 million, has an average generation of 110 million kWh per year.
Strong winds kick up in this region from around October before which the plant had to be operational. The deadline between the contract’s execution and the commissioning of the wind farm was very tight. Our teams were simultaneously facing a challenge of transport option available only during the night for a few hours. To meet the deadline our crew decided to work in two shifts installing two WTG/week.
Sarens deployed the following equipment:
For Transportation:
Extendable trailers
Low bed trailer
Hydraulic conventional trailers
For Erection:
Two 600T Crawler crane
100T Crawler crane
80T Crawler crane
500T hydraulic crane
120T Rough terrain crane
60T Rough terrain crane
32 axle lines of SPMT
Two PPU, 3x5T telehandler, flat bed trailer
The equipment was transported by trailers from the storage yard in Vietnam in five days. Three flatbed trailers, 32 axle-lines of SPMT and 2 PPU at site were deployed for relocation. The equipment was carefully and safely assembled in five days as the hardstand was narrow and unlevelled.
All the tower sections, hub, nacelle, and blades were transported during night due to transport restrictions through public places. Once moved to site, three tower sections, hub, nacelle, three blades each for the twelve WTGs were lifted and installed at a rate of thirty hours/WTG.
Our teams were challenged by heavy rain and strong wind due to which they had to stop the operation in between and then begin installation again to ensure safety. Despite the challenges the installation was successfully competed at a rate of 2WTGs/week. Sarens was awarded and certified for its outstanding performance and lasting contribution of 350,000 safe man-hours without fatality at the Dam Nai wind farm project.
NOTHING TOO HEAVY, NOTHING TOO HIGH

Source Sarens
Headline Photograph Siemens Gamesa
Related news


Sarens New Depot for Hinkley Point C (HPC) nuclear power station

80m Fish Sea Cage Rolled Out by Sarens in Norway
Sarens loads-out the 80m broad fish sea cage at the Norway Royal Salmon`s Arctic Offshore Farming project.