Sarens installs wind turbines in Belgium – Heavy Lift News
3 Jan 2019

Sarens installs wind turbines in Belgium

Sarens PC3800-1 works for Siemens Gamesa to install wind turbines in Belgium

Date 03 January 2019

Sarens worked for FairWind AS, the installation company from Denmark, to install six wind turbines on Siemens Gamesa site located in the municipalities of Gesves and Ohey in Belgium. 

The six wind turbines are of type Siemens SWT-3.2-113 with a power of 3.2 MW with a total height of 150 meteres and rotor diameter of 113m. Once operational, the wind farm will produce the equivalent of the electricity consumption of approximately 12,000 homes in the area. 

Sarens deployed the following equipment: 

  • PC3800-1 LHLF_3 96+12m (15?)
  • LTM1500-8.1 for pre-assembly
  • LTM1130 auxiliary crane 

The equipment was transferred to the site from Sarens’ yard. There were five transfers in total, three normal transfers between the WTGs and two extended tranfers crossing public roads where the crew had to dismount the crane completely. The complete transfer took three days followerd by four days to rig the cranes. 

The Sarens crew lifted the four tower sections, nacelle, and rotor of the turbines to complete the installation. The heaviest section lifted was the nacelle weighing 77T which was lifted at a radius of 22m. 

Despite meeting transfer times and standy due to weather conditions, Sarens’ team took two days per wind turbine to safely complete the installation. 

Source Sarens

Related news