Sarens Completes Heavy Lift Transport of Oversized Tanks in Kazakhstan – Video
Sarens was commissioned by Kazakhstan Petrochemical Industries (KPI) to offload and transport 37 oversized tanks from the KCOI port to the Karabatan Integrated Gas Chemical Complex.
The Karabatan Integrated Gas Chemical Complex, located 33km north-east of Atyrau and around 9km north of Karabatan station, is planned to be operational by the second quarter of 2021. Once completed the project aims at release of export-oriented products with high added value and polymer production for industrial diversification.
The team had to arrange for permissions and approvals from authorities of two regions including the power companies, traffic police, and local civic authorities. CC4000 available at the KCOI port was used to offload the tanks. 126 axle-lines and 8 prime movers were deployed for the transportation of the oversized loads.
The maximum height of the load was 10m with the trailer and the maximum weight was 250t without the trailer. The transport was completed in seven continuous trips by a crew of 35 tackling difficult weather conditions – heavy winds, slippery roads, snow, etc.
According to the Project Manager, Azamat Izteleuov, “Operations like this highlight the need for the right equipment, industry expertise, and a willingness to work tirelessly with city planners and officials to make challenging projects a reality.”
Video
Source Sarens
Related news


Sarens Installs Siemens Generator at Black Point Power Station, Hong Kong

Sarens’ 98m Long Trestle Lift In Mexico
Sarens installed the last section of the assembly plant of General Motors in Ramos Arizpe, Mexico

Sarens’ Twins Remove Parisian Bridge
Sarens successfully removes old bridge using twin barge Karel-Victor