Sarens Commissioned to Lift Swiss Krono Green Energy Project Smoke Stack by Vyncke Clean Energy Technology – Heavy Lift News
28 Sep 2023

Sarens Commissioned to Lift Swiss Krono Green Energy Project Smoke Stack by Vyncke Clean Energy Technology

Sarens used the Demag AC 5.160-1 to successfully lift the smokestack

The Green Energy project at Swiss Krono aims to transform the Sully Sur Loire site and replace around 90% gas consumption with renewable biomass sources. Swiss Krono specialises in the production of construction materials and other wood products. Swiss Krono Company recruited our client Vyncke Clean Energy Technology to replace the old equipment and install the new boiler at their green energy project in Sully sur Loire, France.

In a short rental project, Sarens was commissioned to lift the PCBR2 Smokestack with a diameter of 5m and weighing 18.3t . The challenge was to work under live plant conditions within a tight space and minimal disruption to nearby structures.

The lift was completed within a day. Sarens will be onsite for the next three months to execute multiple lifts.

Sarens is the trusted partner to execute all projects with utmost precision – Big or Small!

 

 