OHT's Osprey Delivers First 8 Jackets for Moray East OWF – Heavy Lift News
7 May 2020

OHT’s Osprey Delivers First 8 Jackets for Moray East OWF

The first eight jacket foundations for the Moray East offshore wind project arrived in the Port of Nigg in Scotland at the weekend, delivered by OHT’s heavy transportation vessel Osprey from the UAE.

The transit took 39 days from Lamprell’s site in Hamriyah, UAE via the Cape of Good Hope on their 12,000 nautical mile journey to the Cromarty Firth.

All 48 of the three-legged jackets fabricated in the UAE, averaging more than 1,000 tonnes and up to 80 metres in height, will be transported over the coming months to the Scottish port utilising three of OHT’s largest open deck semi-submersible heavy transportation vessels.

‘It is great to see the foundations arriving safely to port on schedule’ said Egil Ismar, OHT’s Project Manager. ‘The voyage went very well and the close cooperation between all involved parties during planning, loading and transportation has been remarkable’.

The contract for transportation was awarded last September after several years in close discussions with the project’s foundation EPCI contractor DEME Offshore.

Source OHT