OHT’s Alfa Lift Building Progress

The building of Alfa Lift, the offshore wind foundation installation vessel, is progressing well at CMHI Shipyard in China. Currently 78 of the 162 blocks are installed in the dock. The hull structural steel construction of the remaining blocks is also taking shape; in total 103 of the 162 blocks have reached the NDT completion status.

Source OHT

 