3 Nov 2022

Megalift Sdn. Bhd. Transports 50MW Solar Plant Transformer

Megagift’s Thai partner handled the transportation of a transformer in Thailand from the pick-up location in Thailand to the border with Malaysia at Bukit Kayu Hitam.

 

 

At the border the teams from the 2 partners worked together to jack down the transformer unit before loading it onto Megalift’s multi-axle trailers.

 

 

Once loaded onto their trailer, they started the 170km transport from Bukit Kayu Hitam to the solar energy plant site at Nibong Tebal.

 

 

After traveling on road for more than 170km, the transformer arrived at the site in Nibong Tebal in the state of Penang.

 

 

Lastly, to move the transformer to its foundation, Megalift carried out a jack and skid operation to position it on to the plinth.

 

 

Source Magalift Sdn Bhd