Mammoet Moves 3,900t Dragline 24km on SPMTs in Texas – Heavy Lift News
28 Jan 2025

Mammoet Moves 3,900t Dragline 24km on SPMTs in Texas

Last month Mammoet’s team in Texas was tasked with moving a 3,900t dragline. First the machine was jacked up roughly 1.5m (5 ft.) to be loaded on SPMTs for transport.

The almost 24 km (~15 mile) journey included crossing a state highway, traversing a small creek, and going underneath four major high-voltage lines in order to get to the next mining area.

 

 

Despite weather-related challenges including rain, fog, and some muddy terrain, the machine was carefully moved to its new destination.

 

 

(Hard-) Hats off to all involved on making the move a success!

 