Efficiency Saves Time for Mammoet in Thailand
A smart approach and the right crane saved several days of project time
Mammoet’s expertise delivering end-to-end solutions for projects of this scale led to Borealis and Tecnimont, the plant’s engineering, procurement and construction management (EPCM) partner, awarding it the contract for the transportation and installation of the site’s 35 heaviest pieces of equipment in late 2019. The successful transportation of the plant’s largest component signals the first major milestone during the plant’s two-year construction phase.
Having consulted Borealis on the most efficient delivery timetable, Mammoet’s team of experienced engineers and field workers started preparing the quay for the load-out four days prior to the transportation date. The splitter arrived on a barge from Spain, and once the barge was equipped with ballast pumps and winches, the load-out and transportation operation was executed.
To minimize disruption to both the project’s schedule and the port, transportation of the splitter occurred overnight, after Mammoet had arranged short-term road closures with local authorities.
84 axle lines of SPMT were mobilized to transport the splitter across the 1500m stretch from the Port of Antwerp to the Borealis production site in Kallo.
“Safety is our greatest priority in every operation we deliver. The size of the C3 splitter did not make this job any different,” explains Mammoet Project Manager, Stefan Bostelaar. He continues: “We’ve been planning this operation since the contract was signed last year. Fortunately, we’ve been able to coordinate the operation from our office in Antwerp, and in cooperation with our clients, we’ve scheduled the project to optimize construction timelines.”
A smart approach and the right crane saved several days of project time
This time-saving and cost-efficient method for the float-off was performed for the first time in the Kingdom.