Last Jacket Foundations Delivered to Port of Nigg for Seagreen
To round off the year, Seaway7 have confirmed that the final Seagreen Jacket was delivered to the marshalling yard in Nigg this week, successfully concluding their long-haul transportation scope.
In total, 23 deliveries carrying 114 jackets have been successfully and safely received at the Port of Nigg, through collaboration between Seaway7, SSE Renewables, COSCO, Global Energy Group and Mammoet. Each of the three-legged jacket foundations weighs about 2,000t.
This achievement is the culmination of more than two years of hard work since the EPICI contract was awarded to Seaway7 in June 2020, and sets a new benchmark for a successful jacket fabrication and transport project in the offshore wind industry.
Seaway7 look forward to completing the foundation and cables installation scope for the wind farm in 2023.
Source Seaway7