KAHL Group Moving Mega Loads on Heavy Duty Modules from Goldhofer
At the end of last year, the KARL Group, KAHL Schwerlast & Pieper Schwertransporte, was commissioned to move a total of six huge heat exchangers for two gas liquefaction plants destined for Russia from an engineering works near the port in Haren on the River Ems to the cargo vessel.
Over a period of several months, the individual components had been transported from various production facilities to Barlage GmbH in Haren. There the components were assembled and the final touches made to the heat exchangers.
The six heat exchangers comprised:
- two coolers weighing 658t and measuring 46.33 x 6.22 x 7.32m (LxWxH),
- two coolers weighing 429t and measuring 29.06 x 5.58 x 7.53m (LxWxH),
- two coolers weighing 466t and measuring 32.25 x 6.42 x 6.95m (LxWxH).
The KAHL Group was then tasked with the heavy haulage operation of moving the heat exchangers from the assembly plant to the quay, where two Liebherr heavy-duty LR 1600 crawler cranes were waiting to lift the heat exchangers into the cargo hold of the transport vessel.
Although the route was only about 800 m long, the challenges were enormous due to the need to negotiate the confined spaces on the journey all the way round the harbour.
For moving the 658t cooler, the transport team relied on its trusted heavy-duty modules from the house of Goldhofer in a trailing unit configuration with 2x 12 PST/SL-E axle lines, picking up the giant cargo hydraulically without the use of a crane. The equipment used for the operation was a P 1+1/2 split combination, i.e. with one module divided lengthwise and coupled parallel to a second full module. The advantage of this combination is that it offers appreciably better stability than a single-width transporter on the one hand and requires less space for maneuvering than a double-width P 1+1 combination on the other. Each 12-axle unit was powered by a high-performance 490hp Powerpack. With the 658t load lashed onto the two one-and-a-half width self-propelled transporter combinations, it was quite a feat to negotiate the three 90° bends with a total train length of more than 50m and a load width of 6.43m.

The operating crew had to keep a watchful eye on the steering angle on the two self-propelled module combinations, as the cargo constituted a rigid connection between them.
Careful maneuvering was necessary to avoid a number of permanent obstacles (silos, walls, lighting fixtures, etc.) and various items waiting for collection. With electronic steering on all axles and travel speed reduced to snail’s pace, the experts successfully guided the train through all the narrow sections of the route.
Handling such transport operations without a turntable (which has the advantage of much greater tilt stability) calls for meticulous preparatory work and lots of experience, something that the tried and tested team at KAHL and PIEPER demonstrate on a daily basis. And so, in spite of all the difficulties, the huge cargo reached its destination in good time, and the transport vessel was able to sail on schedule.


Source Goldhofer
Related news


Scheuerle delivers 40 Axel lines of 4th Generation SPMTs to Felbermayr

40 Axel Lines of Cometto MSPE Moves 1,100t Mega Yacht

Baumann’s Goldhofer THP/SL-L Modules Hauling Two Gigantic Heat Exchangers for Linde – Gallery
Could this be a record heavy haulage operation?