31 Dec 2021
Jinert’s Heavy Division was recently in Norrköping the install the new Femöresbron on its final location. This was a demanding project where they deployed much of their equipment.
Step 1 Jacking up the bridge with hydraulic jacks and load on to their SPMTs
Step 2 Transport the bridge from the construction site about 500m on 24 SPMT lines axles
Step 3 Lift the bridge on to barge with their crane
Step 4 Sail down to the final position of the bridge
Manoeuvre the barge into position and lower the brige with hydraulic jacks on to the foundations
Everything went fantastically well thanks to all the great employees and suppliers.
Source