Fagioli’s Big Operations in the Venice Lagoon

Where high-level engineering and operational activities are required for heavy transport and lifting on land and sea, Fagioli is always at the forefront.

 

↓↑  Photographs and Featured Title photograph courtesy of MOSE

 

This is the Mo.s.e., project intended to protect the city of Venice, Italy, and the Venetian Lagoon from flooding.

 

photograph : Fagioli

 

On this particular leg of the whole project, Fagioli has been the inventor, the designer, the builder and final user of the CV.02.EVO.C Gantry Launching System for the removal of the barrier gates for maintenance activity at the Bocca di Lido Treporti in Venice.

 

photograph : Fagioli

 

Activities involved:

  • positioning of the Gantry Launching system onto the cement caisson where the barriers are located.
  • lifting of the barrier out of the water and its positioning onto a barge.
  • sea transport in Venice lagoon; unloading and land transport operations with SPMT straight into the maintenance area.

 

photograph : Fagioli

 

 

The dimensions of each barrier are 20m x 20m x 6m with a weight of 250t.

 

photograph : Fagioli

 

The first barrier section was mobilized in three days.

 

 

photograph : Fagioli

photograph : Fagioli

 

Next step, the maintenance activity and the transport back into the installation area, ready to be operational as soon as possible… and then it repeats all over again one by one with the remaining 77 barriers!

Source Fagioli and MOSE