Cutting-Edge Proton Therapy Technology Installed by Sarens in Nur-Sultan, Kazakhstan.

Sarens Lifting the Varian ProBeam 360.

Sarens was asked by their client Mabetex Group to install the Varian ProBeam 360 multiroom system for Siemens Healthcare at the National Research Oncology Center (NROC) at Kerey and Zhanibek Khans St 3 in Kazakhstan Capital city Nur-Sultan, Kazakhstan.

The multi-room version will be an expandable version of the single room ProBeam 360 solution. Treatments can be delivered with an unmatched combination of speed, flexibility, and cost efficiency.  This cutting-edge proton therapy technology promises to revolutionize cancer treatment in the region.

The project involved assembling more than 200 sub-assembling parts and four heavy lift equipment. Sarens offloaded, stored, organsied, and assembled the parts. All the parts had to be lifted inside the building making them blind lifts. The team made multiple site visits and planned the project precisely. The equipment selected consisted of:

  • 80t mobile crane
  • 7t forklift
  • 500t mobile crane

According to Sarens Project Manager, “We were working in a fully constructed hospital and had to make sure that all heavy lifting operations were carefully executed to ensure that the floors and wall paints are not damaged.” All the components were safely lifted and installed in the estimated duration and the client was satisfied with Sarens team.

 

Featured Title photograph

National Research Oncology Centre in Nur-Sultan, Kazakhstan, courtesy of Mabetex Group

 