Bokalift 2 Completes First Project Offshore Taiwan on Changfang and Xidao OWF

Bokalift 2 has successfully reached her first milestone on the Changfang and Xidao OWF project in Taiwan’s waters

She transported and installed a total of seven jackets for the Changfang and Xidao offshore wind farm, thereby completing the first phase of the foundation installation. After picking up the jackets in the Port of Taipei, the offshore installation work was successfully completed using the unique capabilities of the 4,000t revolving crane that lifted and installed the 72-meter-high and 1,400-ton jackets.

The next mission will be the installation of the remaining pin piles and 52 jackets for this project.

Boskalis would like to thank their client CIP, the vessel crew, project staff, and all other  stakeholders involved for the hard work and excellent cooperation on this project.

Source Boskalis

 