ALE - Giant Experience Key for Taiwan Offshore Wind Project – Heavy Lift News
23 Aug 2019

ALE – Giant Experience Key for Taiwan Offshore Wind Project

In order to move towards energy independence and to attract foreign investment, the Taiwanese Government has set a target of 5.5GW of clean energy by 2025. Despite its advanced infrastructure and industries, as a consequence it is still facing major logistical, engineering and civil infrastructure challenges as it strives to meet this goal.

A key development in pursuit of this target is the Formosa 1 wind farm – the country’s first commercial offshore wind project. To facilitate phase two of its construction, a partner was required with experience of managing complex heavy lifting projects across multiple sectors and continents. ALE and Giant Taiwan were chosen to meet this challenge.

ALE – Giant’s scope was the onshore handling, transportation and storage of wind turbine foundations – consisting of 20 monopiles and also transition pieces. This work began at the monopiles’ fabrication facility in Rostock, Germany, and ended at the Port of Taichung, Taiwan.

In Germany, ALE used a tandem-twin strand jack gantry system to lift the monopiles from the fabricator’s trailers. SPMTs with pre-installed ocean transport cradles were then moved into position underneath the monopiles before load-out onto two flat deck carriers for ocean transportation.

While this was taking place, ALE was developing the storage yard in Taichung from vacant grassland into a marshalling area with the 10t/m ground bearing capacity required to receive all foundation elements. The yard was constructed using reinforced concrete slabs, compliant with local regulations designed to mitigate against earthquakes and typhoons, which are common in the area.

Upon their arrival in Taiwan, load-in of the monopiles was carried out during a narrow tidal window, with two monopiles following one another off the flat deck carriers. Separately, the 465t transition pieces were discharged onto a custom transport frame designed by ALE’s R&D department and fabricated by Giant’s approved local supplier. These were then offloaded onto the storage yard by 1250t capacity cranes.

During the offshore installation campaign, the monopiles and transition pieces will be transported back to the quayside in batches of one and one for load-out by the Seaway Yudin for installation offshore in the Taiwan Strait.

ALE’s vast global experience and Giant’s unique local insight proved to be a winning combination. Having successfully undertaken a wide range of complex ports, civil and offshore projects spanning continents, ALE was well-positioned to deliver the optimal engineering and logistics required. Giant, a local expert with more than 20 years of experience in heavy lifting, was invaluable in liaising with local authorities and dealing with an array of complicated local regulations.

For the load-in in Taiwan, a maximum of 128 axle lines of SPMT was used, in a tandem 4 file 16 configuration. For load-out, 96 axles lines in a 4 file 16 configuration was used, with two sets used for the monopiles and one set for the transition pieces. Crane lifting was performed with Demag CC6800 and CC8800 cranes.

This joint venture allowed the client to orchestrate a large and complex project through a single point of contact; one that encompassed heavy lifting, transportation, sea fastening, civil infrastructure, cargo handling and many other associated services. All equipment, as well as the required operating staff, logistics managers and HSQE staff were readily available, at capacity – and sometimes at short notice.

The monopiles and transition pieces handled during this project’s four-month duration will join installations made during phase one of the Formosa 1 project in 2017, raising generation capacity there from 8MW to 120MW

Source ALE

 

Related news