28 Jun 2024
This week Mammoet’s team supported the launch of a 2,100t railway bridge as a whole structure across the river Oder, near the German-Polish border in Küstrin,.
The changing water level and the strong current made the use of a pontoon impossible. Mammoet’s engineering team came up with another smart solution. With temporary support towers on each side of the river their experienced operations team skidded the 180m long bridge safely to the other side of the river ahead of schedule.
Source