Sarens was recently involved in unloading several wind turbine parts and installing thirteen turbines at a project site in Badamsha, Kazakhstan. The work was performed on behalf of customer GE and project owner ENI.
The cranes were sent from the Sarens base in Atyrau, Kazakhstan, a journey of about 800 kilometres. With the equipment on site, the Sarens crew then needed to unload and install all of the turbine parts in the same location. To do this, they worked in two teams: one unloaded turbine parts using the AC 500-2 and the ATF 130 cranes, and the other erected them using the LR 1600-2 and LTM 1160 cranes.
Source Sarens