Loadout of Hohe See topside at Engie Fabricom Hoboken

Loadout of Hohe See topside at Engie Fabricom Hoboken

14 June 2018

This weekend, the topside for the EnBW Hohe See substation was loaded on the pontoon in Hoboken. The topside will soon set sail toward its destination off the German coast.

The jacket left the Smulders’ yard in Vlissingen on 29 May and is already installed offshore.

The consortium comprising Smulders, Engie Fabricom and CG was contracted in March 2016 to design, supply and install the offshore substation for the EnBW Hohe See Offshore Wind Farm

Loadout of Hohe See topside at Engie Fabricom Hoboken

SOURCE: Smulders


Liked this post?